Burndown TableInitial Estimated EffortWeek
Product Backlog Inventory (PBI)0  1  2  3  4  5  6  7  8  9  10 11 12 13 14 
Team charter 5 5
Initial meeting and app summary5 5
Refined app summary 5 5
Interaction design 10 10
Cognitive walkthrough 5 5
Design review 3 3
Initial github commit 1 1
Domain commit 50 2525
User interface implementation 20 20
Usability test scheduling 5 5
Deployment 10 10
Final design presentation 5 5
Usability testing 10 10
Final review with client 10 10
Remaing Effort 1341291241091011011007550452510100 0
Initial Burndown Graph

Actual Burndown

Project:Antipattern App
Burndown TableInitial Estimated EffortWeek
Product Backlog Inventory (PBI)0  1  2  3  4  5  6  7  8  9  10 11 12 13 14 
Team charter 5 5
Initial meeting and app summary 5 5
Refined app summary 5 5
Interaction design 10 10
Cognitive walkthrough 5 5
Design review 3 3
Initial github commit 1 1
Blockly setup 5 5
Misc. (sidebar, test case entry)10 5 5
User interface implementation 20 5 5 10
Blockly->regex string 5 5
Test case matching 5 3 2
Blockly sideways blocks 10 5 5
Blockly x2 (and/or/functions) 10 10
Regex string->Blockly (stretch) 10
Usability test scheduling 5 5
Deployment 10 10
Final design presentation 5 5
Usability testing 10 10
Final review with client 10 10
Remaing Effort 1491441391241191161059075625235302010